Cravens Pool project is behind schedule. Unfortunately, as with most construction we have been involved with lately, we have experienced delays. Additional required electrical drawings to secure the required electrical permit placed the project 36 days behind schedule. In addition, production time on the steel pool body took longer than the contractor anticipated. And, as of late, weather has stopped work on several days.

City staff are in regular communication with the architect and contractor on the project and is pushing every angle we can to open sometime in late summer and potentially extend the season.